US
New Lahore grid station to start work next month
字号+ Author:Smart News Source:Travel 2025-01-12 13:10:20 I want to comment(0)
LAHORE: The 500kV Lahore (North) grid station is likely to be commissioned partially by next month, paving the way to evacuate power from the Matiari-Lahore High Voltage Direct Current (HVDC) transmission line for supply to the various cities of Gujranwala division through 500kV Nokhar grid station and transmission lines near Gakhar, Gujranwala. The project was delayed due to land acquisition and other administrative issues and was scheduled to be completed last summer. However, according to official sources, the newly constituted board of directors (BoD) took serious notice of the delay, resolving most of the issues in the way of completion. “The transmission lines have already been completed. However, the grid station couldn’t be completed on time due to issues related to land acquisition, as various landowners went to courts. But now, there is no issue in this regard,” an official source in the National Transmission and Despatch Company (NTDC) explained while talking to Dawn on Saturday. Matiari-Lahore line to transmit up to 4,000MW electricity by March According to the official, who requested anonymity, as many as 2,200MW of power is currently being transmitted by the 4,000MW Matiari-Lahore HVDC line. After receiving the power in Alternate Current (AC) from the AC transmission lines, the energy is converted into Direct Current (DC) by a converter station at Matiari (near Hyderabad). After carrying the load in DC mode, the converter station at Lahore (near Balloki) converts the power into AC for onward supply to AC lines. “Four lines from Matiari-Lahore HVDC line’s Balloki converter station have been completed. Two connect to the 500kV New Lahore Sarfraz Nagar (Phoolnagar) grid station for power transmission to Lahore metropolitan city and adjoining areas. One has been laid from the converter station to Nokhar (Gujranwala), and the last one has been completed from the converter station to the motorway (near Sheikhupura). The total length of both lines, which connect Nokhar and Motorway, is 113km, and both were completed in December last year,” the official explained. A senior official, who wished not to be identified, said the Matiar-Lahore line has an installed capacity of 4,000MW, so the NTDC needs power as per demand. “At present, the line is transmitting 2,200MW. However, it will increase by 400MW soon when the 500kV North Lahore grid station has an installation of a transformer and some connectors and starts operating partially in the coming days,” he explained. “And by March next year, three more transformers would be installed, commissioning the project to supply another 1,200MW from the HVDC line. This project would be commissioned fully by Marc,h subject to the availability of all equipment, which is sometimes delayed due to import-related issues. It is pertinent to mention that the Lahore north substation project is being executed under the Second Power Transmission Enhancement Investment Programme — Tranche-3 — in funding collaboration with the Asian Development Bank (ADB).
1.This site adheres to industry standards, and any reposted articles will clearly indicate the author and source;
Related Articles
-
Pakistan, China pledge to high-quality development of CPEC 2.0
2025-01-12 12:54
-
جنوبی کوریا میں طیارے کے حادثے کی تحقیقات تیز، تدفین کی رسومات شروع
2025-01-12 12:29
-
سابق صدر یون کی گرفتاری کا حکم
2025-01-12 12:10
-
رپورٹ: بھارت کا مالدیپ کے صدر معزز کو ہٹانے کی مخالفین کی تحریک سے تعلق
2025-01-12 10:29
User Reviews
Recommended Reads
Hot Information
- Two injured in grenade attack in Jaffarabad
- چین نے زور دے کر کہا ہے کہ اس نے کووڈ کے ڈیٹا شیئرنگ میں کچھ نہیں چھپایا۔
- مونٹی نیگرو کے ریستوران میں فائرنگ سے کئی افراد ہلاک: پولیس
- نیو اورلینز میں نئے سال کے جشن کے موقع پر ایک شخص کی ٹرک چلانے سے دس افراد ہلاک ہوگئے۔
- 2025 to witness beginning of Generation Beta
- اپیل عدالت نے ٹرمپ کے جنسی زیادتی کے کیس میں فیصلے کو برقرار رکھا ہے۔
- کبھی ایسا کچھ نہیں دیکھا: سائبر ٹرک دھماکے کے بعد ایلون مسک کا بیان جس میں جان کا نقصان ہوا
- 2021ء کے بعد سے پاکستان میں 6 افراد کے قتل میں بھارت کا ہاتھ، رپورٹ سے انکشاف
- S Korean court orders arrest of suspended President Yoon
Abont US
Follow our WhatasApp account to stay updated with the latest exciting content